Forum Discussion

PrzywaraL's avatar
PrzywaraL
Copper Contributor
Nov 07, 2023
Solved

Tasks are not visible while trying to link to risks MS Project

I created a project with different tasks, as you can see in the SS. After that I created a risk. You can see the risk in the second SS. When I tried to link the risk to a task, no task where found. ...
  • Paul_Mather's avatar
    Paul_Mather
    Nov 13, 2023

    Hello PrzywaraL ,

    Since making the sync tasks to Project site feature active, have you republished the projects? They will not appear in the Task lists on the Project Sites until the project/s have been published again.

    Paul

Resources