Row height issue

Hello, 

I have been facing recently issue with automatic row adjustment (Microsoft® Project 2016 MSO (Version 2505 Build 16.0.18827.20102) 64-bit): anytime I make any change on any of the rows, Project automatically changes the heigh of some of the rows into random height. Selecting/unselecting Wrap Text does not help - when clicking the Wrap text, the rows are readjusted to single line, but when I make another change in Gant (eg update % Completion), the rows height changes again.  

So basically after every change in gant, I need to select or unselect Wrap Text (the same result

) to get back single line per row view. 

I went throught the forum and tried advices: Bar Styles - check all on row 1, Bar Styles - bars without text, Bars/Layout - decrease the bar heigh. Nothing helped so far. 

Can anobody help, or is it a SW bug? 

 

  • VojtechBednar,

    It may be an issue of corruption of your Gantt Chart view. You might try this:

    1. Switch to any view other than the Gantt Chart view
    2. Open the Organizer (File > Info > Organize Global Template).
    3. Select the Gantt Chart view in the list on the right side and hit Delete

    4. Close out of the Organizer and select your Gantt Chart view. Does the row height stay fixed as you edit?

    John

     

6 Replies

  • Go to view, table, more tables, select the entry table and turn off text wrapping there... or is that what you have already done?

  • I've recently been experiencing an issue in Microsoft Project 2016 (Version 2505 Build 16.0.18827.20102) 64-bit related to automatic row height adjustment. Anytime I make a change to any row, like updating the % Completion—Project, it randomly increases the height of some rows. The problem isn’t resolved by toggling Wrap Text. When I click it, the rows return to a single-line view temporarily, but as soon as I make another edit in the Gantt chart, the row height changes again. So effectively, after every minor update, I have to re-toggle Wrap Text just to maintain a consistent row height. I've already reviewed other forum suggestions, such as: Ensuring all Bar Styles are set to Row 1, Removing bar text in Bar Styles, Adjusting bar height in Bars/Layout settings. Unfortunately, none of these steps have fixed the issue. At this point, I’m wondering whether this is a software bug or if there's a hidden setting that overrides row formatting during task updates. If anyone has found a working solution, I’d appreciate the help. We’re also exploring ways to automate reporting and sync project status updates through third-party tools. If anyone has experience working with a https://i3solutions.com/hire-power-automate-developers/that has dealt with similar formatting behavior via automated flows or extensions, please feel free to share insights. Thanks in advance!

    • John-project's avatar
      John-project
      Silver Contributor

      goharclients03,

      Did you try re-setting your Gantt Chart via the Organizer as I suggested above?

      I'm not aware of any bug in Project relating to this issue and there is no hidden setting.

      John

  • John-project's avatar
    John-project
    Silver Contributor

    VojtechBednar,

    It may be an issue of corruption of your Gantt Chart view. You might try this:

    1. Switch to any view other than the Gantt Chart view
    2. Open the Organizer (File > Info > Organize Global Template).
    3. Select the Gantt Chart view in the list on the right side and hit Delete

    4. Close out of the Organizer and select your Gantt Chart view. Does the row height stay fixed as you edit?

    John

     

    • VojtechBednar's avatar
      VojtechBednar
      Copper Contributor

      Hello John,

      yes, the row height stays fixed now. Thank you!

      • John-project's avatar
        John-project
        Silver Contributor

        VojtechBednar,

        You're welcome and thanks for the feedback.

        I don't recall it ever happening for myself but sometimes part or all of a Project file gets corrupted.