Row height issue

Hello,  I have been facing recently issue with automatic row adjustment (Microsoft® Project 2016 MSO (Version 2505 Build 16.0.18827.20102) 64-bit): anytime I make any change on any of the rows, Proj...
  • John-project's avatar
    Jul 19, 2025

    VojtechBednar,

    It may be an issue of corruption of your Gantt Chart view. You might try this:

    1. Switch to any view other than the Gantt Chart view
    2. Open the Organizer (File > Info > Organize Global Template).
    3. Select the Gantt Chart view in the list on the right side and hit Delete

    4. Close out of the Organizer and select your Gantt Chart view. Does the row height stay fixed as you edit?

    John