Forum Discussion
VojtechBednar
Jul 18, 2025Copper Contributor
Row height issue
Hello, I have been facing recently issue with automatic row adjustment (Microsoft® Project 2016 MSO (Version 2505 Build 16.0.18827.20102) 64-bit): anytime I make any change on any of the rows, Proj...
- Jul 19, 2025
VojtechBednar,
It may be an issue of corruption of your Gantt Chart view. You might try this:
- Switch to any view other than the Gantt Chart view
- Open the Organizer (File > Info > Organize Global Template).
- Select the Gantt Chart view in the list on the right side and hit Delete
4. Close out of the Organizer and select your Gantt Chart view. Does the row height stay fixed as you edit?
John
TrevorATperfectproject
Jul 21, 2025Brass Contributor
Go to view, table, more tables, select the entry table and turn off text wrapping there... or is that what you have already done?