Project Layout Configuration makes Baseline disppearing

When I UNSELECT the "Round bars to whole days" checkbox in the Layout form, the Baseline bars disappears in the Control Gantt view. What is happening?

6 Replies

  • John-project's avatar
    John-project
    Silver Contributor
    carlosmoro,
    Interesting. I've never noticed that before but I'd say it's a bug, although it has apparently been around since the current GUI was introduced in Project 2010. It does work "correctly" with older versions of Project (e.g. Project 2003 under Windows XP).

    I'll consult with one of my colleagues to make sure I'm not missing something.

    John
    • carlosmoro's avatar
      carlosmoro
      Copper Contributor

       

      Thank you John-project


      I've tried several possibilities and failed.

      As a separate discussion, it's really cool to see that it's possible to talk about such specific topics with someone in the world... I can't stop being surprised by this.

       

      About the problem itself, if anyone has any suggestions I'll be happy to use!


      Greetings

       

      • John-project's avatar
        John-project
        Silver Contributor

        carlosmoro 

        You're welcome and thanks for the feedback.

         

        To be honest I never use any of the options in the Layout group and your highlighting the issue about baseline gantt bars disappearing is the first I've heard about it. I think it's one of those options that very few users find useful. You can report it via the Feedback channel in Project, left side of splash screen.

         

        This forum, and other like it, are specifically structured to allow seasoned users of Project to lend their expertise to helping other users. We are all volunteers and do not work for Microsoft and we greatly appreciate user feedback.

         

        John

      • carlosmoro's avatar
        carlosmoro
        Copper Contributor
        Yes Dale !!

        That's what I assume too. But in this case, how can we deal with it?