Forum Discussion
carlosmoro
Jul 10, 2023Copper Contributor
Project Layout Configuration makes Baseline disppearing
When I UNSELECT the "Round bars to whole days" checkbox in the Layout form, the Baseline bars disappears in the Control Gantt view. What is happening?
Jul 10, 2023
All --
Definitely a bug and not how the software should work.
Definitely a bug and not how the software should work.
carlosmoro
Jul 12, 2023Copper Contributor
Yes Dale !!
That's what I assume too. But in this case, how can we deal with it?
Regards
That's what I assume too. But in this case, how can we deal with it?
Regards
- Jul 12, 2023carlosmoro --
There is no workaround for this bug, as far as I can tell. The best I can offer you is that you should not deselect the "Round bars to whole days" checkbox in the Layout form. Sorry, but hope this helps.