Project Layout Configuration makes Baseline disppearing
When I UNSELECT the "Round bars to whole days" checkbox in the Layout form, the Baseline bars disappears in the Control Gantt view. What is happening?
John-project
Jul 10, 2023Silver Contributor
carlosmoro,
Interesting. I've never noticed that before but I'd say it's a bug, although it has apparently been around since the current GUI was introduced in Project 2010. It does work "correctly" with older versions of Project (e.g. Project 2003 under Windows XP).
I'll consult with one of my colleagues to make sure I'm not missing something.
John
Interesting. I've never noticed that before but I'd say it's a bug, although it has apparently been around since the current GUI was introduced in Project 2010. It does work "correctly" with older versions of Project (e.g. Project 2003 under Windows XP).
I'll consult with one of my colleagues to make sure I'm not missing something.
John
Jul 10, 2023
All --
Definitely a bug and not how the software should work.
Definitely a bug and not how the software should work.
- carlosmoroJul 12, 2023Copper ContributorYes Dale !!
That's what I assume too. But in this case, how can we deal with it?
Regards- Jul 12, 2023carlosmoro --
There is no workaround for this bug, as far as I can tell. The best I can offer you is that you should not deselect the "Round bars to whole days" checkbox in the Layout form. Sorry, but hope this helps.