Project for the Web - Allow Team members to edit/view only his task

Hello,

 

Project for the web - I created a project and create a security group for projects. added the team members.

 

Assign the task to teams. Now only task owner should able to edit the percentage complete for the task. 

 

Kindly Suggest 

  • RodFromm's avatar
    RodFromm
    Jan 23, 2024
    Users with a Plan 1 or Plan 3 license with just the default Team Member permissions can edit the project in any way they want. There are few limitations to what Plan 1 license user can do, but it's limited by the license and not the assigned permissions.

    We opened a ticket with Microsoft on this and they confirmed our findings that the assigned license privileges trump assigned permissions.

15 Replies

  • Hello sonika755 ,

    Unfortunately this isn't possible, once the user has edit access to the project via the M365 Group - they can edit all tasks as you have seen. 

    Paul

    • mylogi88's avatar
      mylogi88
      Brass Contributor
      Hi Paul, I am having issues with giving access to people on the Teams that are assigned to the Project for the Web. They can only edit the % Complete and check or uncheck that they are complete. How can the assigned member change dates on their tasks?
      • mylogi88 --

        Pardon me for bumping into this thread. Because of time zone differences, Paul's work day may have already ended.

        To answer your question, team members are only allowed to edit the % Complete value and to mark their tasks as completed. This is by design. Hope this helps.
    • sonika755's avatar
      sonika755
      Copper Contributor
      Thanks Paul for your reply. How the project manager will control the project plan. Example team member can delete the project task and other owner can update the task for another users. can you please suggest.