Project for the Web - Allow Team members to edit/view only his task
Hello, Project for the web - I created a project and create a security group for projects. added the team members. Assign the task to teams. Now only task owner should able to edit the percen...
- Jan 23, 2024Users with a Plan 1 or Plan 3 license with just the default Team Member permissions can edit the project in any way they want. There are few limitations to what Plan 1 license user can do, but it's limited by the license and not the assigned permissions.
We opened a ticket with Microsoft on this and they confirmed our findings that the assigned license privileges trump assigned permissions.
Jan 20, 2024
ProjMgrSA --
Unless I am totally misunderstanding the default permissions in Project for the Web, only the designated project manager can edit the project. Team members, regardless of whether they have a Project Plan 1 or Project Plan 3 license, can only update % Complete and mark tasks as completed. This is just how the software works, at least for the moment. Sorry, but hope this helps.
Unless I am totally misunderstanding the default permissions in Project for the Web, only the designated project manager can edit the project. Team members, regardless of whether they have a Project Plan 1 or Project Plan 3 license, can only update % Complete and mark tasks as completed. This is just how the software works, at least for the moment. Sorry, but hope this helps.
RodFromm
Jan 23, 2024Steel Contributor
Users with a Plan 1 or Plan 3 license with just the default Team Member permissions can edit the project in any way they want. There are few limitations to what Plan 1 license user can do, but it's limited by the license and not the assigned permissions.
We opened a ticket with Microsoft on this and they confirmed our findings that the assigned license privileges trump assigned permissions.
We opened a ticket with Microsoft on this and they confirmed our findings that the assigned license privileges trump assigned permissions.
- Jan 23, 2024RFromm --
OUCH! Thanks for jumping into this thread. Truth be known, I do not spend much time nowadays, given the fact that most of my work is with the Microsoft Project desktop application, Project Online, and Project Server. You insight was helpful. Thanks for sharing.