Project for the Web - Allow Team members to edit/view only his task
Hello, Project for the web - I created a project and create a security group for projects. added the team members. Assign the task to teams. Now only task owner should able to edit the percen...
- Jan 23, 2024Users with a Plan 1 or Plan 3 license with just the default Team Member permissions can edit the project in any way they want. There are few limitations to what Plan 1 license user can do, but it's limited by the license and not the assigned permissions.
We opened a ticket with Microsoft on this and they confirmed our findings that the assigned license privileges trump assigned permissions.
sonika755
Mar 25, 2022Copper Contributor
Thanks Paul for your reply. How the project manager will control the project plan. Example team member can delete the project task and other owner can update the task for another users. can you please suggest.
Paul_Mather
Mar 25, 2022MVP
Hello sonika755 ,
Unfortunately there is nothing out of the box. You could customise it though with custom code. Here is an example of preventing users deleting the project: https://techcommunity.microsoft.com/t5/project-blog/how-to-prevent-a-team-member-from-deleting-a-project-using-a/ba-p/2911074
Paul