Forum Discussion
Project for the Web - Allow Team members to edit/view only his task
- Jan 23, 2024Users with a Plan 1 or Plan 3 license with just the default Team Member permissions can edit the project in any way they want. There are few limitations to what Plan 1 license user can do, but it's limited by the license and not the assigned permissions.
We opened a ticket with Microsoft on this and they confirmed our findings that the assigned license privileges trump assigned permissions.
Hello sonika755 ,
Unfortunately this isn't possible, once the user has edit access to the project via the M365 Group - they can edit all tasks as you have seen.
Paul
- mylogi88Nov 23, 2022Brass ContributorHi Paul, I am having issues with giving access to people on the Teams that are assigned to the Project for the Web. They can only edit the % Complete and check or uncheck that they are complete. How can the assigned member change dates on their tasks?
- Nov 23, 2022mylogi88 --
Pardon me for bumping into this thread. Because of time zone differences, Paul's work day may have already ended.
To answer your question, team members are only allowed to edit the % Complete value and to mark their tasks as completed. This is by design. Hope this helps.- ProjMgrSAJan 20, 2024Copper Contributor
Hi Dale_HowardMVP ,
Our organization have Project plan 3 in addition to Microsoft 365 E5. At the moment all the team members see Limited Access next to the Project name . Is there a possibility to provide team members of Project access to edit tasks wherein they can add tasks and upload attachments? Currently thy can only update %completion.
Please let us know if there is a workaround that can be used.
Otherwise all these edit and upload has to go through only one person that can create a bottleneck.
- sonika755Mar 25, 2022Copper ContributorThanks Paul for your reply. How the project manager will control the project plan. Example team member can delete the project task and other owner can update the task for another users. can you please suggest.
- Paul_MatherMar 25, 2022MVP
Hello sonika755 ,
Unfortunately there is nothing out of the box. You could customise it though with custom code. Here is an example of preventing users deleting the project: https://techcommunity.microsoft.com/t5/project-blog/how-to-prevent-a-team-member-from-deleting-a-project-using-a/ba-p/2911074
Paul