New Enterprise Project Types not showing in New Project Ribbon

I am creating new Enterprise Project Types in Project Online. I have setup site and plan templates to be included with them. After saving them they are showing in the Enterprise Project type list in the settings page, but when I go back to Project Center the only projects that are available in the New ribbon is the default 'Enterprise Project' and 'SharePoint task List' project.

Is there a setting or check mark I may have missed? Thanks!

  • Jedihercules --

    If you specified a Department value for the EPT, then only people with that value specified in their Resource Departments field will be able to see the EPT. Does that help? Let us know.

8 Replies

  • Jedihercules --

    If you specified a Department value for the EPT, then only people with that value specified in their Resource Departments field will be able to see the EPT. Does that help? Let us know.
    • Jay_Dee's avatar
      Jay_Dee
      Copper Contributor

      Hello, I have created Enterprise Project Types and created Project templates that have been uploaded as "templates" however in the drop-down menu, "None" is showing up (as per the image). Could you please advise whether I have missing something in terms of the setup?  Thank you.

      • Jay_Dee --

        By the way, after posting my previous reply, I realized I assumed you are seeing only the None option on the Project Plan Template pick list.  Is that correct?  Let us know.

    • Jedihercules's avatar
      Jedihercules
      Copper Contributor
      Thanks Dale! Yes that was it. It's always something small like that LOL 🙂
      • Dale_HowardMVP's avatar
        Dale_HowardMVP
        MVP
        Jedihercules --

        Well, that was way too easy! Thanks for letting me know. You are more than welcome for the help, my friend. Would you kindly mark my reply as the Best Response to your question? I would appreciate that. Thanks!