Forum Discussion
Jedihercules
May 16, 2023Copper Contributor
New Enterprise Project Types not showing in New Project Ribbon
I am creating new Enterprise Project Types in Project Online. I have setup site and plan templates to be included with them. After saving them they are showing in the Enterprise Project type list in ...
- May 16, 2023Jedihercules --
If you specified a Department value for the EPT, then only people with that value specified in their Resource Departments field will be able to see the EPT. Does that help? Let us know.
Jay_Dee
Feb 03, 2025Copper Contributor
Hello, I have created Enterprise Project Types and created Project templates that have been uploaded as "templates" however in the drop-down menu, "None" is showing up (as per the image). Could you please advise whether I have missing something in terms of the setup? Thank you.
Feb 03, 2025
Jay_Dee --
By the way, after posting my previous reply, I realized I assumed you are seeing only the None option on the Project Plan Template pick list. Is that correct? Let us know.
- Jay_DeeFeb 03, 2025Copper Contributor
Hi Dale, thanks so much for your reply. I did try the steps a number of times and was seeing the "None" option come up when selecting a template for an ET. However, for some reason, after a software update today, I tried it again and it worked. Thanks again.