Forum Discussion

Jedihercules's avatar
Jedihercules
Copper Contributor
May 16, 2023
Solved

New Enterprise Project Types not showing in New Project Ribbon

I am creating new Enterprise Project Types in Project Online. I have setup site and plan templates to be included with them. After saving them they are showing in the Enterprise Project type list in ...
  • Dale_HowardMVP's avatar
    May 16, 2023
    Jedihercules --

    If you specified a Department value for the EPT, then only people with that value specified in their Resource Departments field will be able to see the EPT. Does that help? Let us know.