Forum Discussion
Jedihercules
May 16, 2023Copper Contributor
New Enterprise Project Types not showing in New Project Ribbon
I am creating new Enterprise Project Types in Project Online. I have setup site and plan templates to be included with them. After saving them they are showing in the Enterprise Project type list in ...
- May 16, 2023Jedihercules --
If you specified a Department value for the EPT, then only people with that value specified in their Resource Departments field will be able to see the EPT. Does that help? Let us know.
May 16, 2023
Jedihercules --
If you specified a Department value for the EPT, then only people with that value specified in their Resource Departments field will be able to see the EPT. Does that help? Let us know.
If you specified a Department value for the EPT, then only people with that value specified in their Resource Departments field will be able to see the EPT. Does that help? Let us know.
Jedihercules
May 16, 2023Copper Contributor
Thanks Dale! Yes that was it. It's always something small like that LOL 🙂
- May 16, 2023Jedihercules --
Well, that was way too easy! Thanks for letting me know. You are more than welcome for the help, my friend. Would you kindly mark my reply as the Best Response to your question? I would appreciate that. Thanks!- JediherculesMay 16, 2023Copper ContributorOf course! Thanks again 🙂 I am slowly but surely learning the ins and outs of standing up Project Center w/ Project Professional. I used to know all about Project Server way back in the mid 2000's. Playing a bit of catch up now LOL!