Forum Discussion

KAA_82's avatar
KAA_82
Copper Contributor
Apr 22, 2024
Solved

MS Project Resource Graph

In MS Project Resource Graph, how can I show the Bold Horizontal line indicating the Maximum Units number?

  • John-project's avatar
    John-project
    Apr 24, 2024

    Dale_HowardMVP 

    There ya go, throwing down a challenge. I'll give it a go and see what I can come up with. Stay tuned.

     

    Update (a few minutes later).

    As usual you are correct in that with current versions of Project the bold horizontal line is neither present nor available to display. However, when I stepped into my wayback machine and tried this on Project 2010, not only can I show the bold line but I can also delete it by turning off the bar  styles option "show availability line". Another gotcha from our good friends at MS. Maybe, just maybe, it's an artifact from the assignment units/peak units change that was made back in that time frame.

     

    John

8 Replies

  • KAA_82 

     

    As Jhon and Dale say, the Resource graph showing Peak Units looks like a disaster, but not the Work graph, which seems to work correctly, at least in this example, and without forgetting to check the Show availability line option.

     

    Ignacio

     

  • KAA_82 --

    That is not how the Resource Graph works. It is designed to display only a single value in a column chart format. For example, you can display Cost, Work, Peak Units, Percent Allocation, etc., but you cannot display two values in a combination column chart/line chart (which is what you are describing). Sorry, but hope this helps.
    • KAA_82's avatar
      KAA_82
      Copper Contributor

      Dale_HowardMVP 

      Thank you for your reply.

      In the attached picture there is a bold horizontal black line that separates between Allocated (Blue) and Overallocated (Red) resources. I can not show this line which indicates the Maximum Units. I have tried the GRIDLINES list but couldn't find it there either. Do you know how to show it?

      • John-project's avatar
        John-project
        Silver Contributor

        KAA_82,
        So to answer your question, that horizontal line IS the resource Max Units line. It's just called the "availability" line on the Resource Graph. And apparently you have an older version of Project that has that feature.


        John

Resources