MS Project Resource Graph
- Apr 24, 2024
There ya go, throwing down a challenge. I'll give it a go and see what I can come up with. Stay tuned.
Update (a few minutes later).
As usual you are correct in that with current versions of Project the bold horizontal line is neither present nor available to display. However, when I stepped into my wayback machine and tried this on Project 2010, not only can I show the bold line but I can also delete it by turning off the bar styles option "show availability line". Another gotcha from our good friends at MS. Maybe, just maybe, it's an artifact from the assignment units/peak units change that was made back in that time frame.
John
Thank you for your reply.
In the attached picture there is a bold horizontal black line that separates between Allocated (Blue) and Overallocated (Red) resources. I can not show this line which indicates the Maximum Units. I have tried the GRIDLINES list but couldn't find it there either. Do you know how to show it?
KAA_82,
So to answer your question, that horizontal line IS the resource Max Units line. It's just called the "availability" line on the Resource Graph. And apparently you have an older version of Project that has that feature.
John