MS Project Resource Graph

In MS Project Resource Graph, how can I show the Bold Horizontal line indicating the Maximum Units number?
  • John-project's avatar
    John-project
    Apr 24, 2024

    Dale_HowardMVP 

    There ya go, throwing down a challenge. I'll give it a go and see what I can come up with. Stay tuned.

     

    Update (a few minutes later).

    As usual you are correct in that with current versions of Project the bold horizontal line is neither present nor available to display. However, when I stepped into my wayback machine and tried this on Project 2010, not only can I show the bold line but I can also delete it by turning off the bar  styles option "show availability line". Another gotcha from our good friends at MS. Maybe, just maybe, it's an artifact from the assignment units/peak units change that was made back in that time frame.

     