MS Project custom fields on Dataverse

I'm working on project for the web + Project accelerator (model driven).

My mpp file has some custom fields such as: custom_1 , custom_2,...
After importing that mpp to Project Accelerator, where / I tried to look for those custom fields on the projecttask table (Dataverse) but no result.

 

Do you have any solutions ?

Thanks
=======
Update:
For better explain, I have a project on P4W, I create some custom fields (free text). Will those field be written on Dataverse's tables ? How can i get those fields to build some further solutions / features in Project Accelarator ? 

  • Hello cuonglt0105 ,

    Custom fields added in to the task in Project for the web are not available in the Dataverse tables.

    Paul

11 Replies

  • cuonglt0105 --

    When you import a Microsoft Project (*.mpp) file into Project for the Web, there are a number of features that are stripped from the *.mpp file. One of those features is custom fields. You will need to recreate those fields and populate the data in your projects. Sorry, but hope this helps.
    • cuonglt0105's avatar
      cuonglt0105
      Tin Contributor
      Thanks Dale but maybe you mis-understanded my question. For example, I have a project on P4W, I create some custom fields (free text). Will those field be written on Dataverse's tables ? How can i get those fields to build some further solutions / features in Project Accelarator ?
      • Paul_Mather's avatar
        Paul_Mather
        MVP

        Hello cuonglt0105 ,

        Custom fields added in to the task in Project for the web are not available in the Dataverse tables.

        Paul