Forum Discussion
cuonglt0105
Jul 05, 2023Tin Contributor
MS Project custom fields on Dataverse
I'm working on project for the web + Project accelerator (model driven). My mpp file has some custom fields such as: custom_1 , custom_2,... After importing that mpp to Project Accelerator, where /...
- Jul 05, 2023
Hello cuonglt0105 ,
Custom fields added in to the task in Project for the web are not available in the Dataverse tables.
Paul
Jul 05, 2023
cuonglt0105 --
When you import a Microsoft Project (*.mpp) file into Project for the Web, there are a number of features that are stripped from the *.mpp file. One of those features is custom fields. You will need to recreate those fields and populate the data in your projects. Sorry, but hope this helps.
When you import a Microsoft Project (*.mpp) file into Project for the Web, there are a number of features that are stripped from the *.mpp file. One of those features is custom fields. You will need to recreate those fields and populate the data in your projects. Sorry, but hope this helps.
- cuonglt0105Jul 05, 2023Tin ContributorThanks Dale but maybe you mis-understanded my question. For example, I have a project on P4W, I create some custom fields (free text). Will those field be written on Dataverse's tables ? How can i get those fields to build some further solutions / features in Project Accelarator ?
- Paul_MatherJul 05, 2023MVP
Hello cuonglt0105 ,
Custom fields added in to the task in Project for the web are not available in the Dataverse tables.
Paul
- MRAJan 17, 2025Copper Contributor
Hello Paul,
I was looking on how to import form .mpp to Power Builder (aka dataverse) and I found the text that follows on the link below.
May be is innacurate? or the functionalities of Project for the WEB have been changed since? I will appreciate your comments, Thanks
"
What gets imported?
Project for the web does not have all the same features as Project Desktop. However, we try to import all your relevant information so you can still effectively work on your projects.
- Project: Your project name and start date will be imported.
- Tasks: Your tasks will be imported with the correct hierarchy, start & finish dates, duration, effort, effort completed, and % complete.
- Dependencies: All finish-to-start dependencies will be imported.
- Constraints: ASAP, start no earlier than, and finish no earlier than constraints will be imported.
- Custom Fields: You can import up to 10 local custom fields from your .mpp file.
"