Forum Discussion
MS Project custom fields on Dataverse
- Jul 05, 2023
Hello cuonglt0105 ,
Custom fields added in to the task in Project for the web are not available in the Dataverse tables.
Paul
Hello cuonglt0105 ,
Custom fields added in to the task in Project for the web are not available in the Dataverse tables.
Paul
- MRAJan 17, 2025Copper Contributor
Hello Paul,
I was looking on how to import form .mpp to Power Builder (aka dataverse) and I found the text that follows on the link below.
May be is innacurate? or the functionalities of Project for the WEB have been changed since? I will appreciate your comments, Thanks
"
What gets imported?
Project for the web does not have all the same features as Project Desktop. However, we try to import all your relevant information so you can still effectively work on your projects.
- Project: Your project name and start date will be imported.
- Tasks: Your tasks will be imported with the correct hierarchy, start & finish dates, duration, effort, effort completed, and % complete.
- Dependencies: All finish-to-start dependencies will be imported.
- Constraints: ASAP, start no earlier than, and finish no earlier than constraints will be imported.
- Custom Fields: You can import up to 10 local custom fields from your .mpp file.
"
- PewPewProjectJun 25, 2024Brass Contributor
Hi Paul_Mather,
You seem to be quite well informed, so I hope you don't mind me asking - I've gone through a number of answers/articles related to this topic but haven't quite seen the answer I'm looking for.. the custom columns are not stored in the Dataverse, but where are they stored? no one seems to have provided this information, and the data would need to be stored somewhere? do you or any other knowledgeable people in the forums know how/where the data is stored?
At this point I don't even care if it's not in a location I can pull from, not knowing where its stored is eating me up.
Thanks in advance for any assistance and help across these forums!
Tenielle- James320Jun 26, 2024Copper Contributor
PewPewProject, Agreeded, If I could be able to read and write from custom columns, I would be able to build some great apps that could possible remove a significant number or excel project management documents from my company. more cohesive everything
- MelanieEBFeb 01, 2024Copper Contributor
Paul_Mather Hi Paul, is there any update on this? Do you know if there are plans to make the Project for the Web custom fields available in Dataverse? Thank for any hint!
- daibtJul 05, 2023Brass Contributor
- Paul_MatherJul 06, 2023MVP
Unfortunately not daibt
- daibtJul 06, 2023Brass Contributor
Do you have any solutions that helps me to get information in custom field in Project for the Web and update it into Accelerator?