Forum Discussion
stpstein
Nov 06, 2019Copper Contributor
Help Please
Hi, I'm trying to create a visual display of an agenda. I really want basically a Gantt chart, but instead of dates, I want it in times. It's a sum of 3 days that I want to display, starting for 8:00...
Riny_van_Eekelen
Nov 07, 2019Platinum Contributor
Not sure about what you mean by "the sum of 3 days to display", but have a look at the attached workbook. It displays three tasks on an axis (8 AM to 8 PM). The yellow cells contain the chart data. The gray cells at the top ar just for information. I used them to "calculate" the min and max value for the horizontal axis. Perhaps this helps you find a solution for your problem.