project server
168 TopicsMS Project Master file won’t allow Duration/Deadline edits
I’m troubleshooting an unusual issue with a long-standing Microsoft Project Master/consolidated file containing multiple linked subprojects. After replacing one subproject with its latest monthly version, certain fields within that subproject cannot be edited from the Master file. Specifically, I cannot edit fields such as Duration or Deadline, while other fields, such as Text and Baseline fields, can still be edited normally from the Master. I’m sensing the theme has to do with fields that require calculation. More context: This issue arrived after we migrated MPP files from a cloud server to an on-prem server. Previous month’s Cloud server MPP file works fine in the Consolidated environment The master file creates the issue when I replace the cloud-based MPP with the current month on-prem version. Troubleshooting completed: The subproject works normally when opened directly. I created a brand-new blank MPP to use as the Master file and inserted the exact same subproject. Duration and Deadline are editable through the new Master. In the new consolidated file and repeated the normal download from on-prem/replacement process. Everything works correctly. The problem therefore appears to follow the existing Master MPP, rather than the subproject. F9/recalculation does not resolve the issue. The existing Master has been used for a long time and contains multiple inserted/linked subprojects and external relationships. Important constraint: I want to avoid rebuilding the Master or use a repair method that regenerates existing task UIDs. A higher-level consolidated schedule relies on the existing UIDs.326Views0likes3CommentsCalendar View in SharePoint Project Sites
In Project Server, a SharePoint site is created for each project. On that SharePoint site, there's a list of late tasks and upcoming tasks. There is also a Calendar view, but it looks like you have to manually add items to the calendar. How do I make it so that this Calendar will automatically be populated with Upcoming Tasks as shown on the SharePoint web page for each project?108Views0likes0CommentsHow to download MS Project Plans along custom fileds including data
I have Project plans in project online. I am opening the plan in ms project, custom fields data is getting loaded. But when i try to save the file in local desktop, schedule data is saving but custom fields data is not coming only column names are coming. How to save the file along with task level custom fields with data in local desktop110Views0likes0CommentsGeneric Resources - Team Assignment Pool Yes or No?
Our On-Prem Project Server environment was set up with Generic Resources marked "No" for Team Assignment Pool. It seems we would want this to be a "Yes", so that tasks assigned to a Generic resource would be visible by Project Server users with the same role, and those users could then self-assign those tasks and provide updates. Our generic resources are meant to represent a "pool" of people in different labor categories, so that we can look at potential areas of under or over utilization. It seems that marking them as a Team Assignment Pool would reflect our intended use. For most of our generic resources, we don't plan to replace them with a specific person (such as production work). However, for some resources such as engineers, we would like them to be able to self-assign tasks and give updates in Project Server. Is there a particular reason to keep our Generic Resources marked "No" for Team Assignment Pool? Does changing to "Yes" affect their capacity, availability, or Work/Cost values?Solved321Views0likes3CommentsMS PROJECT 2019 UPDATE and Purchasing Options
HI We are currently using Microsoft Project Professional 2019 desktop version, but we are facing challenges with its reporting limitations. Specifically, the software can only display a maximum of 75 rows in its reports. As our weekly reports often exceed this limit, we find ourselves spending considerable time on manual entries. For our monthly reports, we can manage the filtering process to avoid this limitation, but the weekly reports require a hierarchical structure to display task statuses, and unfortunately, there is no workaround for this constraint. While researching this issue, I found discussions indicating that the 2025 version of Microsoft Project can display up to 150 rows, which would help us address our challenges. I have a couple of questions: 1. Does the new version of Microsoft Project 2025 indeed support the display of up to 150 rows? 2. What is the best approach for upgrading: subscription or standalone? 3. Could you provide pricing information and tell us where we can obtain it? Thank you! Best regards, Teshome HPU PMO Office267Views0likes1CommentProject Server Column Header/Gantt Chart misalignment
We are using On-Premises Project Server, and in all views (Project, Project Center, Resources, etc.), the Column Headers are larger than normal, so that the bar in the Gantt Chart does not align with the project/task/resource associated with it. The browser we are using is Edge but I switched to Chrome and had the same issue. Does anyone know what causes this and how to fix it?91Views0likes0CommentsWorkload by week/ month export to Excel
I like to use Visual report, but that doesn’t work.. I have MSProject 2016 and office 365. so I have tried to use save as (export) as xls. But I can’t get the load or week or month. anyone that can help out setup in table format. I think… the I can build the rest in Excel if needed br runeSolved405Views0likes4CommentsLOE Tasks in Project Server
What is the proper way to reflect LOE (Level Of Effort) tasks in MS Project? For example, adding a task showing the PM working 10% of his time on the project, for the duration of the project. If we simply give that task a duration equal to the project, then Project cannot determine the correct Critical Path of the project. In addition, if the project duration changes, the PM will have to manually change the duration of the PM task. If we try linking this task with SS and FF relationships, the duration remains 1 day unless we input the duration, in which case we still have to update the duration as the project progresses. I have tried creating a hammock LOE task by copying and pasting links to the first and last tasks, as described in TenSix Consulting articles https://tensix.com/creating-loe-tasks-in-microsoft-project/ and https://tensix.com/more-about-level-of-effort-tasks-in-microsoft-project/ . However, this does not work in my version of Project Professional. I am only able to link either the starting date or finish date, but not both. Does anyone here have experience with scheduling this type of LOE task in MS Project? We are using on premises Project Server. We want to schedule this type of PM oversight task to plan for the estimated hours of PM time over the span of the project, have the task duration update dynamically if the project duration changes, and be able to status this PM task during the project to reflect the "actual" and "remaining" hours for the task as the project progresses.125Views0likes0CommentsUse Save for Sharing for Colleagues who Don't have Project Pro?
You need Project Professional to open schedules from Project Server and publish updates/changes. We have individuals in our organization who only have Project Standard, but need to provide input into the schedule. Should we use the Save for Sharing feature so that these people can update the schedule in their version of Project Standard, then the schedule Owner in Project Server can then check in the project with those updates? If we do this, how do we handle the Enterprise Objects (resources, calendar, and custom fields) which the Project Standard user doesn't have access to?Solved246Views0likes2CommentsSchedule Opens in Read-Only Mode from Conference Room Computer
In Project Server, a Project Manager opens his schedule on a conference room computer, but it opens Read Only mode and the PM is not able to check it out and edit/publish the project. We made sure it was not already checked out, and the PM is able to open, edit and publish this schedule from his work station. As far as we can tell, this problem only occurs when opening this one schedule from the conference room computer. We have cleared the cache as described in this handy article: https://www.dalehowardmvp.com/force-check-in-stuck-projects/ but this didn’t solve the issue. I have seen another article https://www.dalehowardmvp.com/how-to-fix-corrupted-files/ about using Save for Sharing to correct possibly corrupted schedules. My question is: would doing this cause any issues since we are accessing the schedule from a conference room? We do not want to adversely affect the way the PM opens this project from their work station. Does anyone have an experience with schedules opening from the PM’s work station but opening Read-Only when accessing PWA from a conference room computer? Would Save for Sharing help in this instance? Thank you264Views0likes2Comments