How to download MS Project Plans along custom fileds including data

I have Project plans in project online. I am opening the plan in ms project, custom fields data is getting loaded. But when i try to save the file in local desktop, schedule data is saving but custom fields data is not coming only column names are coming. How to save the file along with task level custom fields with data in local desktop

1 Reply

  • PingCadence's avatar
    PingCadence
    Copper Contributor

    Those columns are enterprise custom fields. Their definitions live in Project Online's Enterprise Global, not in the plan itself, so when you save a local copy Project keeps the column headings but drops the values. Two ways to get the data out while you can still open the plan from Project Online:

    1. Copy each enterprise field into a local field, then save. With the plan open from the server, insert an unused local field of the same type (Text1–30, Number1–20, Date1–10, Flag1–20 or Cost1–10). Click the enterprise column's heading to select it, press Ctrl+C, click the first cell of the local column and press Ctrl+V. Then right-click the local column's heading, choose Custom Fields and rename it to match. Local fields are stored in the .mpp, so the values survive Save As. Lookup-table values come across as plain text, which is usually fine for an archive copy.

    2. Export to Excel. File > Save As > Excel Workbook, then in the Export Wizard pick Selected Data > New map > Tasks and add the enterprise fields to the field list. The values export as long as the plan was opened from Project Online.

    If you have a lot of plans, a short VBA macro that loops through the tasks and writes each enterprise field into its local twin saves a lot of clicking. Test it on one plan first.

     

    One caution: do this while the plans can still be opened from the server. The local file on its own doesn't contain the enterprise values, so there's nothing to recover from it later.