Forum Discussion

Molalenge's avatar
Molalenge
Brass Contributor
Apr 16, 2024

UPDATE PROJECT DIALOGUE BOX

I run a portfolio of 60 small and large projects and submit a weekly status report to my sponsor.  Recently, we started updating projects: Set 0%- 100% complete. Unfortunately, we don't see the "Late" status report of some tasks, as the software assumes everything is on track. Is there another feature we can add to our weekly report to see late or slipping tasks while maintaining the auto-update feature? 

 

Let me know if you have any questions.

 

Thanks.

Teshome 

 

 

 

 

 

  • Molalenge,

    Short answer, no. By using auto update you are telling Project to assume everything is up to date with respect to the current date, or status date if different from the current date.

     

    Is there a way to still see late or slipping tasks? Yes, don't use auto update, as those two features are mutually exclusive.

     

    John

  • John-project's avatar
    John-project
    Silver Contributor

    Molalenge,

    Short answer, no. By using auto update you are telling Project to assume everything is up to date with respect to the current date, or status date if different from the current date.

     

    Is there a way to still see late or slipping tasks? Yes, don't use auto update, as those two features are mutually exclusive.

     

    John

Share