Forum Discussion
Molalenge
Apr 16, 2024Brass Contributor
UPDATE PROJECT DIALOGUE BOX
I run a portfolio of 60 small and large projects and submit a weekly status report to my sponsor. Recently, we started updating projects: Set 0%- 100% complete. Unfortunately, we don't see the "Late...
- Apr 16, 2024
Short answer, no. By using auto update you are telling Project to assume everything is up to date with respect to the current date, or status date if different from the current date.
Is there a way to still see late or slipping tasks? Yes, don't use auto update, as those two features are mutually exclusive.
John
John-project
Apr 16, 2024Silver Contributor
Short answer, no. By using auto update you are telling Project to assume everything is up to date with respect to the current date, or status date if different from the current date.
Is there a way to still see late or slipping tasks? Yes, don't use auto update, as those two features are mutually exclusive.
John
- MolalengeApr 18, 2024Brass Contributor
- John-projectApr 18, 2024Silver ContributorMolalenge,
You're welcome and thanks for the feedback.
John- MolalengeApr 18, 2024Brass ContributorJohn,
I forgot to ask you. Can you disable the auto update feature, or you simply not use the application for future use? Make sense? Thanks. Again.