Forum Discussion

Molalenge's avatar
Molalenge
Brass Contributor
Apr 16, 2024
Solved

UPDATE PROJECT DIALOGUE BOX

I run a portfolio of 60 small and large projects and submit a weekly status report to my sponsor.  Recently, we started updating projects: Set 0%- 100% complete. Unfortunately, we don't see the "Late...
  • John-project's avatar
    Apr 16, 2024

    Molalenge,

    Short answer, no. By using auto update you are telling Project to assume everything is up to date with respect to the current date, or status date if different from the current date.

     

    Is there a way to still see late or slipping tasks? Yes, don't use auto update, as those two features are mutually exclusive.

     

    John

Resources