Forum Discussion

mintvivek's avatar
mintvivek
Copper Contributor
Apr 12, 2024
Solved

Having problem with linking the tasks in project tool

Hi, 

I am facing a problem with MS Project tool. I have created different tasks and linked them and put them in different phases. Also, I have given the title or project name at the top of task list. Ideally, every phase should display the duration as per their task list, but it is not happening. The first phase is showing overall duration of the project which is wrong. I have tried linking and unlinking of the tasks several times but in vain. Please help me and guide what wrong I have done.

 

Thanks in advance..

    • mintvivek's avatar
      mintvivek
      Copper Contributor
      Hi,
      Did you receive the pics? If not, please let me know.
    • mintvivek's avatar
      mintvivek
      Copper Contributor

      Ignacio_Martin 

      For your convenience, I have split the task list in two parts and since I am a beginner, I am not creating a huge task list. Please check the above two screenshots and help me. Thanks.

  • Hello.
    Can you confirm if the tasks are in Auto Scheduled and not Manuallly in the Task Mode column? If not, try putting the phase summary tasks in Auto mode. Precisely the manually scheduled mode is an option that the user can put what he wants without considering the subtasks.
    Ignacio

    • mintvivek's avatar
      mintvivek
      Copper Contributor

      Ignacio_Martin 

       

      First of all, thanks for the response and secondly, all the tasks including Summary are in "Auto Scheduled" Mode only.

Resources