Having problem with linking the tasks in project tool
Hi, I am facing a problem with MS Project tool. I have created different tasks and linked them and put them in different phases. Also, I have given the title or project name at the top of task list...
- Apr 12, 2024
Ignacio_Martin
Apr 12, 2024Steel Contributor
Hello.
Can you confirm if the tasks are in Auto Scheduled and not Manuallly in the Task Mode column? If not, try putting the phase summary tasks in Auto mode. Precisely the manually scheduled mode is an option that the user can put what he wants without considering the subtasks.
Ignacio
- mintvivekApr 12, 2024Copper Contributor
First of all, thanks for the response and secondly, all the tasks including Summary are in "Auto Scheduled" Mode only.