May 02 2023 07:20 AM
Hi All,
You may find my question stupid, but after a long hassle, I decided to ask for help.
Given: Say I input a new summary task for the project and say this summary task has 5 tasks. The time period for each task is 1 week (5 days) and the time gap between tasks is 3 weeks (15 days). I set the project time to be calculated in days. After all that, my summary task shows that the total amount of working time is 100 days (working + gap), instead of 25 days of actual work.
Pop-quiz: how can I set the summary task to show the actual amount of working time instead of the total time including gaps?
Sorry if it all sounds confusing, I tried to be as specific as I could.
Thanks to everyone in advance!
P.S. I use MP 365
May 02 2023 07:46 AM
May 02 2023 08:19 AM
May 02 2023 10:12 AM
Use a custom Duration field (say Duration1) with formula = [Duration] and under the calculation for task and group summary rows, tick the Rollup checkbox and select Sum from the dropdown.
May 02 2023 10:34 AM
May 03 2023 03:30 AM
May 03 2023 08:26 AM