Forum Discussion
ICNARC261
May 02, 2023Copper Contributor
Actual number of days working on the task VS period of time to complete the task
Hi All, You may find my question stupid, but after a long hassle, I decided to ask for help. Given: Say I input a new summary task for the project and say this summary task has 5 tasks. The ti...
PlannersPlace
May 02, 2023Brass Contributor
Use a custom Duration field (say Duration1) with formula = [Duration] and under the calculation for task and group summary rows, tick the Rollup checkbox and select Sum from the dropdown.
- May 02, 2023Clever trick. I like it. But the formula fails if any of the tasks overlap in the summary section. But still a nice trick anyway! It would work for this user's particular situation.