Actual number of days working on the task VS period of time to complete the task
Hi All, You may find my question stupid, but after a long hassle, I decided to ask for help. Given: Say I input a new summary task for the project and say this summary task has 5 tasks. The ti...
PlannersPlace
May 02, 2023Brass Contributor
Use a custom Duration field (say Duration1) with formula = [Duration] and under the calculation for task and group summary rows, tick the Rollup checkbox and select Sum from the dropdown.
May 02, 2023
Clever trick. I like it. But the formula fails if any of the tasks overlap in the summary section. But still a nice trick anyway! It would work for this user's particular situation.