This project is already extracted in another computer or in another PWA instance
Hello,
In my Project pro or in my PWA instance I am the only user, so I don't understand how this file can be extracted by somebody else. I'm not able to archive this project.
What can I do to archive this project ?
Thanks for your help
Hello Robert0842 ,
You possibly have the project checked out for editing in PWA directly? Access this page {PWAURL}/_layouts/15/pwa/Admin/ForceCheckin.aspx and see if the project is listed there and checked out to you. If it is, check it back in and the problem should be sorted.
Paul
2 Replies
Hello Robert0842 ,
You possibly have the project checked out for editing in PWA directly? Access this page {PWAURL}/_layouts/15/pwa/Admin/ForceCheckin.aspx and see if the project is listed there and checked out to you. If it is, check it back in and the problem should be sorted.
Paul
- Robert0842Copper ContributorThanks a lot Paul !
That worked !