Forum Discussion
Robert0842
Oct 28, 2021Copper Contributor
This project is already extracted in another computer or in another PWA instance
Hello, In my Project pro or in my PWA instance I am the only user, so I don't understand how this file can be extracted by somebody else. I'm not able to archive this project. What can I do ...
- Oct 28, 2021
Hello Robert0842 ,
You possibly have the project checked out for editing in PWA directly? Access this page {PWAURL}/_layouts/15/pwa/Admin/ForceCheckin.aspx and see if the project is listed there and checked out to you. If it is, check it back in and the problem should be sorted.
Paul
Paul_Mather
Oct 28, 2021MVP
Hello Robert0842 ,
You possibly have the project checked out for editing in PWA directly? Access this page {PWAURL}/_layouts/15/pwa/Admin/ForceCheckin.aspx and see if the project is listed there and checked out to you. If it is, check it back in and the problem should be sorted.
Paul
- Robert0842Oct 29, 2021Copper ContributorThanks a lot Paul !
That worked !