This project is already extracted in another computer or in another PWA instance
Hello, In my Project pro or in my PWA instance I am the only user, so I don't understand how this file can be extracted by somebody else. I'm not able to archive this project. What can I do ...
- Oct 28, 2021
Hello Robert0842 ,
You possibly have the project checked out for editing in PWA directly? Access this page {PWAURL}/_layouts/15/pwa/Admin/ForceCheckin.aspx and see if the project is listed there and checked out to you. If it is, check it back in and the problem should be sorted.
Paul
Paul_Mather
Oct 28, 2021MVP
Hello Robert0842 ,
You possibly have the project checked out for editing in PWA directly? Access this page {PWAURL}/_layouts/15/pwa/Admin/ForceCheckin.aspx and see if the project is listed there and checked out to you. If it is, check it back in and the problem should be sorted.
Paul
Robert0842
Oct 29, 2021Copper Contributor
Thanks a lot Paul !
That worked !
That worked !