Sub task duration update
Rachely747,
When there is a break in the "active" time (working time) of a task's span such as when an assigned resource has specific non-working days or the task has a split, the duration for that task is the active span. However, a summary line is not a task and the duration of a summary line is start to finish.
In your example, the resource holidays puts a break in the subtask active span, hence the total span (duration) is unchanged. But the break in the subtask adds to the total span at summary level.
Hope this helps.
John
- John-projectSilver Contributor
Rachely747,
When there is a break in the "active" time (working time) of a task's span such as when an assigned resource has specific non-working days or the task has a split, the duration for that task is the active span. However, a summary line is not a task and the duration of a summary line is start to finish.
In your example, the resource holidays puts a break in the subtask active span, hence the total span (duration) is unchanged. But the break in the subtask adds to the total span at summary level.
Hope this helps.
John- Rachely747Copper ContributorThank you for clarifying, John