Sub task duration update
- Feb 26, 2022
Rachely747,
When there is a break in the "active" time (working time) of a task's span such as when an assigned resource has specific non-working days or the task has a split, the duration for that task is the active span. However, a summary line is not a task and the duration of a summary line is start to finish.
In your example, the resource holidays puts a break in the subtask active span, hence the total span (duration) is unchanged. But the break in the subtask adds to the total span at summary level.
Hope this helps.
John
Rachely747,
When there is a break in the "active" time (working time) of a task's span such as when an assigned resource has specific non-working days or the task has a split, the duration for that task is the active span. However, a summary line is not a task and the duration of a summary line is start to finish.
In your example, the resource holidays puts a break in the subtask active span, hence the total span (duration) is unchanged. But the break in the subtask adds to the total span at summary level.
Hope this helps.
John
- John-projectFeb 27, 2022Silver ContributorRachely747,
You're welcome and thanks for the feedback. If I answered your question, please consider marking my response as the answer.