Forum Discussion

Rachely747's avatar
Rachely747
Copper Contributor
Feb 25, 2022
Solved

Sub task duration update

I have MSP 2021. If I assign a resource with specific holidays to a sub task with specified hours, the duration of the sub task doesn't increase based on the holiday but the duration of the summary ta...
  • John-project's avatar
    Feb 26, 2022

    Rachely747,
    When there is a break in the "active" time (working time) of a task's span such as when an assigned resource has specific non-working days or the task has a split, the duration for that task is the active span. However, a summary line is not a task and the duration of a summary line is start to finish.

    In your example, the resource holidays puts a break in the subtask active span, hence the total span (duration) is unchanged. But the break in the subtask adds to the total span at summary level.

    Hope this helps.
    John

Resources