Forum Discussion

FernandoFalchiane's avatar
FernandoFalchiane
Brass Contributor
Feb 27, 2024
Solved

Status of a task that has already expired appearing as "future task"?

I'm controlling my project very rigorously, but I hardly use the task status column, even though it's necessary. Today I was printing a report with overdue tasks and I missed many tasks, I looked at the cause and I see that some tasks that are overdue have the status of future tasks, where is the error now?

Example:

Task NameDurationStartFinishStatus

XYZ

5 days

24/02/24

29/02/24

Future Task

Looking:

The green line is today and the task hasn't even started yet in the gantt.

  • Hello Fernando.
    Project considers task status relative to the status date, not today's date.

    Possibly the Status Date of your project is before 02/24/24, which is when these two tasks begin.
    Regards
    Ignacio

2 Replies

  • Hello Fernando.
    Project considers task status relative to the status date, not today's date.

    Possibly the Status Date of your project is before 02/24/24, which is when these two tasks begin.
    Regards
    Ignacio

    • FernandoFalchiane's avatar
      FernandoFalchiane
      Brass Contributor

      Ignacio_Martin Wow thank you very much! I'm a beginner and I'm still learning. What you told me made a lot of sense, in my head it updated itself according to the current day, not that it would be a manual process for me to update the date.

Resources