Forum Discussion
FernandoFalchiane
Feb 27, 2024Brass Contributor
Status of a task that has already expired appearing as "future task"?
I'm controlling my project very rigorously, but I hardly use the task status column, even though it's necessary. Today I was printing a report with overdue tasks and I missed many tasks, I looked at ...
- Feb 27, 2024
Hello Fernando.
Project considers task status relative to the status date, not today's date.Possibly the Status Date of your project is before 02/24/24, which is when these two tasks begin.
Regards
Ignacio
Ignacio_Martin
Feb 27, 2024Steel Contributor
Hello Fernando.
Project considers task status relative to the status date, not today's date.
Possibly the Status Date of your project is before 02/24/24, which is when these two tasks begin.
Regards
Ignacio
FernandoFalchiane
Feb 28, 2024Brass Contributor
Ignacio_Martin Wow thank you very much! I'm a beginner and I'm still learning. What you told me made a lot of sense, in my head it updated itself according to the current day, not that it would be a manual process for me to update the date.