Report of nominal deliveries versus real deliveries

Hi everyone,

I created a Project with different deliveries in different days. For example, on 17th April I have to deliver 2 boxes (nominal delivery).

Due to delays in the project the delivery of the two boxes will be on 23rd April and 27th April.

Is there a report which shows the cumulative deliveries Vs the real deliveries?

I mean on x-coordinate the time (days, weeks...) and on x-coordinate the cumulative sum of deliveries.

Thank you for your help

11 Replies

  • John-project's avatar
    John-project
    Silver Contributor

    argaii

    Can you get a report like that? Yes, but not with any of Project's report formats (unless I've missed a trick). For a graph like you describe, I would export Project data to Excel and then create the graph there.

     

    John

    • argaii's avatar
      argaii
      Copper Contributor

      Hi John-project 

      I also tought to export the data of the MS Project file to an Excel, but this is not a good solution for two reasons:

      - I'm creating this MS Project file for the projects of the company where I work. The reports are useful not for me but for other colleagues which will have access to this MS Project, it will be shared

      - The final purpose is to use MS Project online, in order to link it also woth MS Planner and send the tasks to the people which are working on the project and consequently the updates for the reports, everything in the cloud and shared

       

      Anyway thank you for the suggestion 🙂

      • John-project's avatar
        John-project
        Silver Contributor
        argaii,
        If you can live without the graph, a few custom fields can provide the data in Project but it may still require a macro.

        John