Report of nominal deliveries versus real deliveries
Hi everyone, I created a Project with different deliveries in different days. For example, on 17th April I have to deliver 2 boxes (nominal delivery). Due to delays in the project the delivery of t...
- Feb 19, 2024argaii,
You might find the following link useful in understanding the various Project options, particularly the response from my colleague Dale Howard.
https://answers.microsoft.com/en-us/msoffice/forum/all/question-about-various-versions-of-microsoft/b9acf061-aacb-4986-8e9c-8125c05c76c3.
John
John-project
Feb 16, 2024Silver Contributor
Can you get a report like that? Yes, but not with any of Project's report formats (unless I've missed a trick). For a graph like you describe, I would export Project data to Excel and then create the graph there.
John
- argaiiFeb 16, 2024Copper Contributor
Hi John-project
I also tought to export the data of the MS Project file to an Excel, but this is not a good solution for two reasons:
- I'm creating this MS Project file for the projects of the company where I work. The reports are useful not for me but for other colleagues which will have access to this MS Project, it will be shared
- The final purpose is to use MS Project online, in order to link it also woth MS Planner and send the tasks to the people which are working on the project and consequently the updates for the reports, everything in the cloud and shared
Anyway thank you for the suggestion 🙂
- John-projectFeb 16, 2024Silver Contributorargaii,
If you can live without the graph, a few custom fields can provide the data in Project but it may still require a macro.
John- argaiiFeb 17, 2024Copper ContributorHi,
Do you know this macro?
It's not a theme of survival, but I don't work alone and the deliveries through time are really important for our customers 😉