Remaining Duration

Hi, I have inserted a new column to show 'Remaining Duration' of a number of tasks on a certain date. I have shown a very small sample of the Gantt Chart below, showing just one site. As you can see I only have one asset unfinished with a duration of 2 days, but the 'Overall Site' for some reason shows 8.83 days. Can anyone explain this to me, and how to make it display correctly? Thank you.

 

 

  • DawkiT --

    The Asset 5 task contains a task split (the ... section in the Gantt bar). The split is pushing the remaining 2 days of the task's Gantt bar out into the future, which is why you see a Duration of 8.83 days for the Overall Site summary task. Hope this helps.
    • DawkiT's avatar
      DawkiT
      Copper Contributor
      Hi Dale, Thank you for your reply, however the split is intentional as we have to come away from the site for a while, but the remaining duration on site is still 2 days although not continuous. Regardless I cannot see where 8.83 days comes from.

Resources