Forum Discussion
DawkiT
Jun 28, 2022Copper Contributor
Remaining Duration
Hi, I have inserted a new column to show 'Remaining Duration' of a number of tasks on a certain date. I have shown a very small sample of the Gantt Chart below, showing just one site. As you can see ...
Jun 28, 2022
DawkiT --
The Asset 5 task contains a task split (the ... section in the Gantt bar). The split is pushing the remaining 2 days of the task's Gantt bar out into the future, which is why you see a Duration of 8.83 days for the Overall Site summary task. Hope this helps.
The Asset 5 task contains a task split (the ... section in the Gantt bar). The split is pushing the remaining 2 days of the task's Gantt bar out into the future, which is why you see a Duration of 8.83 days for the Overall Site summary task. Hope this helps.
DawkiT
Jun 28, 2022Copper Contributor
Hi Dale, Thank you for your reply, however the split is intentional as we have to come away from the site for a while, but the remaining duration on site is still 2 days although not continuous. Regardless I cannot see where 8.83 days comes from.