Remaining Duration
Hi, I have inserted a new column to show 'Remaining Duration' of a number of tasks on a certain date. I have shown a very small sample of the Gantt Chart below, showing just one site. As you can see ...
Jun 28, 2022
DawkiT --
The Asset 5 task contains a task split (the ... section in the Gantt bar). The split is pushing the remaining 2 days of the task's Gantt bar out into the future, which is why you see a Duration of 8.83 days for the Overall Site summary task. Hope this helps.
The Asset 5 task contains a task split (the ... section in the Gantt bar). The split is pushing the remaining 2 days of the task's Gantt bar out into the future, which is why you see a Duration of 8.83 days for the Overall Site summary task. Hope this helps.
- DawkiTJun 28, 2022Copper ContributorHi Dale, Thank you for your reply, however the split is intentional as we have to come away from the site for a while, but the remaining duration on site is still 2 days although not continuous. Regardless I cannot see where 8.83 days comes from.