Forum Discussion

phcma's avatar
phcma
Copper Contributor
Jan 20, 2022
Solved

Project for the Web export to excel only columns in Grid view

When using the 'Export to Excel' feature it exports all columns. Is it possible to export only what is visible in the grid view? Or can I feature request a checkbox system for exports.   Thanks.  ...
  • Dale_HowardMVP's avatar
    Jan 20, 2022
    phcma --

    From your description, it sounds like you are using Project for the Web and NOT Project Online as you state in the title of your question. Assuming that you are using Project for the Web, then the answer to your question is no. It is not possible to export only what is displayed in the Grid view. The Export to Excel automatically exports all standard columns, plus any custom columns you have created. If there are columns you do not want to see in the resulting Excel worksheet, simply delete them. Hope this helps.

Resources