Project Remaining Duration as of Status Date

In a Project schedule, The % Complete entered during an update doesn't seem to push the task Finish Date as it should. The task has a Start date of 6/9/25, Finish date of 9/23/25, duration of 14.95 weeks. The Status date is 9/12/25, Actual start 6/9/25 (on schedule) but progress is 2% Complete, Remaining Duration is 13.45 wks. When I click Update Project and reschedule uncomplete work to start as of Status Date (9/12/25) the Finish Date remains 9/23/25. Shouldn't the Finish Date push to approx. 12/12/2025 based on the % complete and remaining duration? There are a handful of tasks in this schedule with a similar issue, so I would like to find out what causes this, so we can make the task Finish Dates update as you would expect when updating % complete and Remaining Duration on tasks as of the status date. If someone could point me in the right direction it would be much appreciated.

There are no date constraints on the task, and "Split In-Progress tasks" is selected in the Schedule Options.

We are using a 4 day a week/10 hours a day calendar.

We assign Generic Resources to tasks but this particular task is NOT resource loaded.

This task is linked with both a predecessor and successor, and both the predecessor and successor are statused 100% complete. Could this be why Project isn't updating the Finish Date for this task, since its successor is complete?

We are using Project Server. This project has been published with the status date of 9/12/25.

 

7 Replies

  • stevenj's avatar
    stevenj
    Copper Contributor

    BrettPhifer_SCI,

     

    First off all, im sorry for reply from your post, because I am new here and I dont know how to post on Microsoft Community Hub.

     

    I also have the same issue, the task Start Date is 20 Nov 2025 and Finish Date is 7 Dec 2025. The status date is 28 Nov 2025 and %Complete is 10%, but when I input 10% in %complete column the Finish Date should be delayed. I would like to know how to solve this problem, because I want to monitor every task and know what should I do to catch up the project, should it be increase the manpower or works.

     

    Thanks.

  • John-project's avatar
    John-project
    Silver Contributor

    BrettPhifer_SCI,

    Yes, the finish date should be pushed out based on the parameters you stated.

    I notice you are not using the Standard calendar, so what is your Project calendar and working hours?

    Do you have any resources assigned to the task(s)?

    Are there any predecessors or successors for the task(s)? A screen shot would be helpful.

    If necessary, would you be willing to send me your file?

    John

    • BrettPhifer_SCI's avatar
      BrettPhifer_SCI
      Copper Contributor

      John,

       

      Thank you for responding. I'm hesitant to provide screen shots and/or file sharing due to potentially sharing sensitive info. But below are responses to your questions:

      Calendar - we use a 4 day a week/10 hours a day calendar

      Resources - we do assign Generic Resources to tasks but this particular task is NOT resource loaded.

      Predecessors/Successors - yes, this task is linked with both and I just noticed, both the predecessor and successor are statused 100% complete. Could this be why Project isn't updating the Finish Date for this task, since its successor is complete?

       

      Thank you

      • John-project's avatar
        John-project
        Silver Contributor

        Brett,

        Sorry, I've submitted a detailed response to this thread twice now and neither is showing. Something is awash with this forum.

        John