Yes, the finish date should be pushed out based on the parameters you stated.
I notice you are not using the Standard calendar, so what is your Project calendar and working hours?
Do you have any resources assigned to the task(s)?
Are there any predecessors or successors for the task(s)? A screen shot would be helpful.
If necessary, would you be willing to send me your file?
John
- BrettPhifer_SCISep 18, 2025Copper Contributor
John,
Thank you for responding. I'm hesitant to provide screen shots and/or file sharing due to potentially sharing sensitive info. But below are responses to your questions:
Calendar - we use a 4 day a week/10 hours a day calendar
Resources - we do assign Generic Resources to tasks but this particular task is NOT resource loaded.
Predecessors/Successors - yes, this task is linked with both and I just noticed, both the predecessor and successor are statused 100% complete. Could this be why Project isn't updating the Finish Date for this task, since its successor is complete?
Thank you
- John-projectSep 18, 2025Silver Contributor
Brett,
Sorry, I've submitted a detailed response to this thread twice now and neither is showing. Something is awash with this forum.
John
- BrettPhifer_SCISep 18, 2025Copper Contributor
I replied and it's gone now as well. Can you try to email your response to email address removed for privacy reasons?