Forum Discussion
BrettPhifer_SCI
Sep 16, 2025Copper Contributor
Project Remaining Duration as of Status Date
In a Project schedule, The % Complete entered during an update doesn't seem to push the task Finish Date as it should. The task has a Start date of 6/9/25, Finish date of 9/23/25, duration of 14.95 w...
stevenj
Nov 28, 2025Copper Contributor
BrettPhifer_SCI,
First off all, im sorry for reply from your post, because I am new here and I dont know how to post on Microsoft Community Hub.
I also have the same issue, the task Start Date is 20 Nov 2025 and Finish Date is 7 Dec 2025. The status date is 28 Nov 2025 and %Complete is 10%, but when I input 10% in %complete column the Finish Date should be delayed. I would like to know how to solve this problem, because I want to monitor every task and know what should I do to catch up the project, should it be increase the manpower or works.
Thanks.