Project for web - calendar

Hi,

on Project for web i've different plan with same/different resource.

I've created a "calendar resource" with its own work calendar, then i'm using this resource as calendar template for all my plan.

As i found here: https://learn.microsoft.com/en-us/project-for-the-web/create-and-apply-a-work-calendar

Now i've this problem: resource A that need to have different calendar for each plan.

So for example:

  • resource A works on 01/15 in plan A
  • resource A not works on 01/15 in plan B

Is it possibile to achieve? How can i do that if my resource is the same? So same calendar?

Can i create custom calendar for each plan but also for each resource in it?

Thanks!

  • Hello Saaam1165 ,

    That is correct, the resource is a single entity that can be added to multiple plans. The resource can only have 1 calendar.

    Paul

3 Replies

  • Saaam1165's avatar
    Saaam1165
    Copper Contributor

    Hi Paul,

    i need that because our resources could work in more department so i need to schedule that on a calendar for each department plan.

     

    But from my understanding i could only manage the resource calendard (in common with all plans) or the plan calendar (common for all resources in plan), is that right? No other ways?

     

    Thanks!

     

     

     

    • Paul_Mather's avatar
      Paul_Mather
      MVP

      Hello Saaam1165 ,

      That is correct, the resource is a single entity that can be added to multiple plans. The resource can only have 1 calendar.

      Paul

  • Hello Saaam1165 ,

    I'm not sure that would be expected, for the same resource to have a different resource calendar for each project that one resource worked on? The resource calendar should be representative to the hours that resource works. 
    Are you needing this to avoid "Resource A" be double booked on projects?