Project for web - calendar

Hi, on Project for web i've different plan with same/different resource. I've created a "calendar resource" with its own work calendar, then i'm using this resource as calendar template for all my ...
  • Paul_Mather's avatar
    Paul_Mather
    Jan 16, 2025

    Hello Saaam1165 ,

    That is correct, the resource is a single entity that can be added to multiple plans. The resource can only have 1 calendar.

    Paul