Forum Discussion
Saaam1165
Jan 15, 2025Copper Contributor
Project for web - calendar
Hi, on Project for web i've different plan with same/different resource. I've created a "calendar resource" with its own work calendar, then i'm using this resource as calendar template for all my ...
- Jan 16, 2025
Hello Saaam1165 ,
That is correct, the resource is a single entity that can be added to multiple plans. The resource can only have 1 calendar.
Paul
Paul_Mather
Jan 16, 2025MVP
Hello Saaam1165 ,
I'm not sure that would be expected, for the same resource to have a different resource calendar for each project that one resource worked on? The resource calendar should be representative to the hours that resource works.
Are you needing this to avoid "Resource A" be double booked on projects?